"No Information" after September 1st
Glen,
Indeed, the free/busy publishing schedule works like you describe it and
changing the free/busy publishing to more months will show more "future"
data in a meeting invite.
Are your users configured in Cached or Online mode?
How did you configure the "4 month" setting? Did you change this for all
users?
Here's a test:
1. Make sure User1 is configured for 6 months of free/busy publishing
2. Have User1 add a test appointment to their own calendar for October 1.
3. Have User1 exit and restart Outlook (this ensures their free/busy data is
published)
4. Have User2 open a meeting invite and add User1 to a meeting on October 1
Does User2 see the appointment for User1 on October 1 in the free/busy grid
of the meeting?
--
Thanks
greg mansius [MSFT]
Microsoft Office Outlook Support
This posting is provided "AS IS" with no warranties, and confers no rights.
Please do not send email to this address, post a reply to this newsgroup.
"Glen" wrote in message
...
When scheduling meetings in Outlook, anything scheduled after September
1st
show up for the users as No Information. Is this because of the 'publish
2
months of calendar information" setting in Outlook?
It is the middle of July, so does that mean Outlook will only displays
July
and August as the 2 months? If so, I set my settings and another user to
display 4 months but still see the same issue after September 1st.
A fix or clarification on what is going on here would be helpful.
I am using Outlook 2007. Others use Outlook 2003. I have a single
Exchange
2003 SP 2 server running on a Windows 2003 server.
Thanks.
|