Default Creating Task sometimes collapses group

If I create a Task item and then look at the Tasks in Table View (grouped by
Category), I sometimes find that the Group to which the new Task was
assigned is collapsed. I can expand that group, and all is fine, but if I
create another Task in another Category, that will sometimes cause that
group to collapse.

I haven't been able to figure out exactly when this happens, but it seems to
happen more often when I'm switching between Views. i.e, if I create a Task
while in one Table View (filtered for high priority items only) and then
switch to the other Table View (no filter), the new task is in a collapsed
group.

Anything I can do about this?

I'm using OL 2003, WinXP Pro SP2.